Powergrid Nagapattinam Transmission Limited Project Elements
Project Element | Progress | Project Start Date | Implementing Agency | Sector | Region | Voltage ratio(kV/kV) | Capacity MVA | Land Acquisition | Civil works Completed | Structure,transformers, Substation eqpt Received |
Structure,transformers, Substation eqpt erected |
Capacity Tested | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Extn. at 01 non bay at 400KV Madhugiri S/stn |
|
29-03-2012 | Power Grid Corporation of India Limited | Government | South | 400 | 100% | 20% | 20% | 5% | 0 | ||
Extn. at 02+01 nos bays at 400KV New Salam (Dharmapuri) (provision one 63 MVAR Line Ractor) |
|
29-03-2012 | Power Grid Corporation of India Limited | Government | South | 400 | 100% | 40% | 30% | 10% | 0 | ||
Extn. at 02 nos bays at 400KV Nagapattinam Pooling Station (GIS) (provision one 63 MVAR Line Ractor) |
|
29-03-2012 | Power Grid Corporation of India Limited | Government | South | 400 | 100% | 50% | 40% | 20% | 0 |
Project Element | Progress | Project Start Date | Implementing Agency | Sector | Region | ckts | voltage Level | Circuit kilometers | Total Location | Stubs Cast | Towers Erected | Stringing Completed | ||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
No's | % of Completion | No's | % of Completion | ckm | % of Completion | |||||||||||
765 kV S/C Salem-Madhugiri |
|
29-03-2012 | Power Grid Corporation of India Limited | Government | South | S/C | 765 | 250 | 574 | 312 | 54% | 217 | 38% | 58 | 23% | |
765 kV D/C Nagapattinam Pooling Station-Salem |
|
29-03-2012 | Power Grid Corporation of India Limited | Government | South | D/C | 765 | 500 | 543 | 521 | 96% | 465 | 86% | 200 | 40% |