Back

Powergrid Nagapattinam Transmission Limited Project Elements

Project Element Progress Project Start Date Implementing Agency Sector Region Voltage ratio(kV/kV) Capacity MVA Land Acquisition Civil works Completed Structure,transformers,
Substation eqpt Received
Structure,transformers,
Substation eqpt erected
Capacity Tested
Extn. at 01 non bay at 400KV Madhugiri S/stn
16.25%
29-03-2012 Power Grid Corporation of India Limited Government South 400 100% 20% 20% 5% 0
Extn. at 02+01 nos bays at 400KV New Salam (Dharmapuri) (provision one 63 MVAR Line Ractor)
27.5%
29-03-2012 Power Grid Corporation of India Limited Government South 400 100% 40% 30% 10% 0
Extn. at 02 nos bays at 400KV Nagapattinam Pooling Station (GIS) (provision one 63 MVAR Line Ractor)
37.5%
29-03-2012 Power Grid Corporation of India Limited Government South 400 100% 50% 40% 20% 0
Project Element Progress Project Start Date Implementing Agency Sector Region ckts voltage Level Circuit kilometers Total Location Stubs Cast Towers Erected Stringing Completed
No's % of Completion No's % of Completion ckm % of Completion
765 kV S/C Salem-Madhugiri
33.08%
29-03-2012 Power Grid Corporation of India Limited Government South S/C 765 250 574 312 54% 217 38% 58 23%
765 kV D/C Nagapattinam Pooling Station-Salem
62.6%
29-03-2012 Power Grid Corporation of India Limited Government South D/C 765 500 543 521 96% 465 86% 200 40%